construction begins of the taichung metropolitan opera house, designed by toyo ito.
the ground-breaking ceremony for the second-stage main construction of the taichung
metropolitan opera house was held on dec. 3, 2009.
the theater is expected to cost NT.36 billion (US5 million) and will take over four
years to complete. the opera house is now on track for a december 2013 ribbon-cutting.
according to taichung city officials, the project was put up for bid five times over the past
several years but failed to attract suitable tenders due to associated engineering challenges.
while other major cities in taiwan are all known for something, taichung, a city of roughly
1 million residents whose name means 'central taiwan' in chinese, has trouble finding
anything to distinguish itself from taiwan's other metropolises. today it is seen as one of
the most cultural cities in taiwan.


model of the taichung metropolitan opera house

the main structure will be formed with several connecting curved walls, inlaid floors,
inlaid interior and exterior walls, and a core service wall. the curved wall structure will
be formed with 58 curved wall units, creating many complications in building steel bar
reinforcements and steel trusses. the construction technique is the first of its kind in the
world of architecture and has never been seen before in the taiwanese engineering industry,
which meant that many local construction companies failed to show interest in participating
in the project. in order to acquire the cooperation of the ideal company, the city government
visited many potential collaborators and finally signed a contract with lee ming construction.
wu chun-shan, president of lee ming construction, said building such a structure containing
three-dimensional curved walls was generally thought impossible.
'but we are making the impossible possible'.


drawing of the taichung metropolitan opera house


drawing of the taichung metropolitan opera house


integrated in the landscape


spatial organization


left: audience circulation, right: VIP and office circulation


ito’s work has  been highly concerned with the notions of an all-encompassing, ever expanding space.


a nearly 4m large-scale model. ito made full-scale structural models to simply prove its integrity.



continuos surfaces in an open structure which actively engages its surroundings in all directions
and creates great opportunities for artists and visitors, stage and auditorium, interior and exterior.


toyo ito calls this space the 'sound cave', a horizontally and vertically continuous network.


toyo ito
portrait © designboom



illustration by studio toyo ito

issues of the environment, resources, and energy

1. recycling of rainwater and sewage
the rain falling on the large roof surface will be collected and filtered for use in
irrigation and sprinkling for landscaping plants, etc. sewage from the facility will be
processed in a purification tank to approximately 5ppm BOD and 5ppm SS, and then
reused as an intermediate water supply for purposes such as toilet flushing.

2. use of eco-materials
the majority of materials used will be recyclable eco-materials. this helps to limit the
environmental load and conserve resources, thereby contributing to the reduction of
carbon dioxide emissions and prevention of global warming.

3. adjusting the surrounding environment for energy savings
when adjusting the environment of an architectural space, it is not enough to devote
one's energies solely to the load inside the building. it is also essential to arrange the
environment outside the building in a way that reduces the load inside the building.
in this plan, we have given consideration to increasing greenery, creating shade, and
using the evaporative latent heat of water.


part 1

part 2


part 3


section drawing

part 1


part 2


part 3

construction process

the structural system is developed together with the construction
method to realize the freeform geometry in rational and efficient manner.
the freeform concrete surfaces are shotcrete (spray concrete). it is commonly
utilized for tunnel construction and suitable for curved surface. it can be shot
horizontally or vertically. rather than constructing doubly curved formwork that is
expensive and time consuming on site, the temporary structure in the void creates
faceted surfaces that best-fit the finished surface. between the temporary steel work,
expanded metal mesh is expanded metal mesh spans between the temporary steel
work to act as faceted formwork. 150 mm thick concrete can be shot at one time.
the surface layer of 25 mm is shot separately without large aggregate to achieve
smooth surface finish. concrete thickness varies between 200 mm at the top floor
and 350 mm at the bottom.


challenging technique

sprayed concrete construction method

typically, an expanded metal mesh is used as a permanent back shutter to which the
the reinforcing mesh is affixed. the concrete is sprayed onto the expanded metal
and the reinforcement is fully enclosed. the concrete is typically sprayed using one of two
methods. with the dry process, the dry constituents of the concrete are mixed in a portable
batching plant and the water is added to the mix at the nozzle. with the wet process, the
water is added to the batching plant and premixed with the dry constituents and the wet concrete
is sprayed from the nozzle. the benefits of the wet process are that there is greater control over
the concrete mix as the concrete is often mixed off site by ready-mix contractors and delivered in lorries.
it is common practice to apply the concrete in two layers. the first thick layer is usually applied using
the wet process. once sufficiently cured, a second, thin finishing layer is then applied using the dry process.

it is essential that the finished product is cured appropriately to mitigate shrinkage and to ensure that
design strength is achieved. spraying concrete is a messy process. some concrete will rebound and
some will pass through the expanded metal back shutter. it may be necessary to install temporary
protection to avoid polluting the surrounding area.



grand theatre


black box


play house

site area: 57,685 square meters
floor area: 43,264 square meters

2009 seat grand theatre 4,450 m2
800 seat playhouse 1,770 m2
200 seat black box 520 m2

backstage space 2,630 m2

other space 16,090 m2
management space 1,850 m2
arts plaza 6,000 m2
arts/creative workshop 3,100 m2
total 36,410 m2

anita db
03.23.10  
6
I am excited to see its completion.
It will be one of the more complicated architecture built!
Excited   03.23.10
hes the best it doesnt get better thna toyo ito congratulations master
ak   03.23.10
Very exciting, elegant exterior. Wish I could better grasp the opera hall.
D. Barber   03.24.10
US million to be built???
Sounds very low budget.
I've seen English government has spent couple of million pounds for meaningless project such as "Big Bang" by H.
.........maybe the article got wrong exchange rate...
foreign exchange bank   03.24.10
competition design Music Centre Ghent, Belgium
Toyo Ito 2004

image of the model
GentRepresent   03.24.10
Toyo is the man!
SHOPinc/Sohee   03.25.10

toyo ito: 311 starting over from point zero

architecture | 12.21.11

toyo ito gives a candid account of japan after the tsunami and how the personal stories of community members sparked his 'house-for-all' campaign. 

0

venice biennale 2012: japan pavilion preview

architecture | 11.09.11

the japan foundation presents the emergency and temporary housing project home-for-all, the post-disaster reconstruction of the city of kamaishi, led by toyo ito together with kumiko inui, sou fujimoto and akihisa h...

1

toyo ito architecture museum - complete

architecture | 10.31.11

situated on the island of omishima, the project is the first museum in japan that is dedicated to the work of an individual architect.

1

lazerian paper light shades

READER'S SUBMISSION

lazerian launch a new range of paper light shades named after the stars that define the vertices,
which make up the nort...

solar winds cultural arts center

READER'S SUBMISSION

the solar winds cultural arts center is a design proposal for a large solar and wind powered structure dedicated to a wide var...

video

starry night interactive anima

art

translating the artist's paint daubs into particles governed by fluid dynamics, petros vrellis has created an interactive anima...

inga sempé: stockholm f

design

within the airy structure, the french designer has created the feeling of a large, open space apartment, furnished in a way tha...

RENAULT 4 ever behind-the-scenes

DESIGNBOOM COMPETITIONS thousands of you entered from across the world; now take an exclusive video look

'horsey' by eungi kim

DESIGNBOOM COMPETITIONS 'horsey' by eungi kim from korea is one of the shortlisted design entries from m
video

SELFPROMO - january 17 - march 17

DESIGN - AEROBICS how to present yourself in a creative world. different approaches to make sure your work is brought to the attention of the people that 'matter'...

POP UP - january 17 - march 17

DESIGN - AEROBICS don’t blink or you’ll miss it! in this course we’ll look at temporary structures, from living quarters and exhibition stands to container stores...
designboom news
340,294 subscribers

keep up to date with recent articles and upcoming events.
to receive both newsletters please check 2 boxes.

DAILY - see sample BIWEEKLY -see sample
© copyrights 2000 - 2012 designboom, all rights reserved. all material published remains the exclusive copyright of designboom.
no contents, including text, photographs, videos, etc. may be reproduced in whole or in part without the written consent of designboom. in addition,
no material or contents may be reproduced on the world wide web by techniques of mirroring, framing, posting, etc. without the written consent of designboom.